# Delivery approach tailoring note

Draft text for a program management plan update, or similar document, when a contract or policy names a specific agile framework. Review it with your contracting authority. This is not legal advice.

## Purpose

This update describes how the program will tailor its agile delivery approach to align planning with the program's contract milestones, budget cycle and vendor release schedule, while keeping agile team practices.

## What stays the same

- Long-lived, cross-functional teams
- Iterative delivery with built-in quality and a shared Definition of Done
- Regular demonstrations to business owners
- Status reporting at the existing frequency

## What changes

- Increment planning events are replaced by a half-day quarterly business review and monthly backlog replenishment.
- Planning is anchored to the program's milestone register, with baseline, forecast and actual dates for each milestone.
- Work is managed in four lanes: expedite, fixed date, standard and investment.
- Architecture reviews and leadership decisions are tracked as work items.

## Measures reported

| Measure | Replaces or supplements |
|---|---|
| Milestone health and forecast accuracy | Increment predictability |
| Flow time and throughput | Velocity |
| Deployment frequency, lead time, change failure rate, recovery time | Self-assessments |

For one transition quarter, the program will report both the previous and the new measures.

## Transition

Cutover occurs at an increment boundary after a go or no-go decision. If the decision is no-go, the current approach continues for one more quarter.


---