# Lane policy

Lanes, also called classes of service, say how each kind of work is treated. Leadership sets the capacity split each quarter at the business review. Boards show the split and WIP live.

| Lane | Policy | Typical share | WIP policy |
|---|---|---|---|
| Expedite | Production outages, security fixes, safety or regulatory findings. Pulled immediately and allowed to break WIP limits. | Under 5% of capacity | One item per team at a time |
| Fixed date | Work tied to a real external date: a launch, a regulatory deadline, a customer or contract commitment, a peak season, a vendor release window. Started early enough to finish at the 85% forecast. | 20 to 40% | Start by the last responsible date, not before |
| Standard | Ranked business work. Business owners re-rank it monthly; teams pull from the top. | 40 to 60% | Limit by team; pull, don't push |
| Investment | Architectural runway, technical debt, automation, discovery and learning. A protected share, not leftovers. | 10 to 20% | A standing allocation reviewed each quarter |

## Entry rules

- **Expedite:** only for production outages, security fixes, and safety or regulatory findings. The delivery lead decides; the sponsor is informed the same day.
- **Fixed date:** must link to a milestone in the register and carry a target date. Start no later than the 85% forecast allows.
- **Standard:** ranked monthly by business owners at replenishment.
- **Investment:** owned by the lead architect or platform lead; reviewed quarterly against the agreed share.

## Our split this quarter

| Lane | Share | Agreed at | Review on |
|---|---|---|---|
| Expedite | ___% | | |
| Fixed date | ___% | | |
| Standard | ___% | | |
| Investment | ___% | | |


---