# Quarterly business review run book

The quarterly business review replaces PI Planning. It is a half-day decision meeting for about 20 to 30 people. Teams keep planning their own work continuously.

## Purpose

Decide, for the coming quarter:

1. The capacity split across the four lanes
2. Milestone commitments and any milestones at risk
3. The top priorities for each platform or product line
4. Risks that need leadership action

## Preparation (two weeks, about four people)

| When | What | Owner |
|---|---|---|
| Two weeks before | Pull flow, delivery and milestone data for the last quarter | Flow lead |
| Two weeks before | Update forecasts for every milestone in the register | Portfolio controls |
| One week before | Each platform lead drafts a one-page brief: outcomes, top ten, risks | Platform leads |
| One week before | Architecture runway and risk brief | Lead architect |
| Three days before | Circulate the pre-read; collect questions | Flow lead |

## Agenda (four hours)

| Time | Session | Output |
|---|---|---|
| 0:00 | Last quarter in numbers: milestones, flow, delivery, planning hours | Shared view of reality |
| 0:30 | Milestone register: what is at risk and why | Decisions or escalations |
| 1:15 | Lane split for next quarter | Agreed percentages |
| 1:45 | Break | |
| 2:00 | Platform briefs, 10 minutes each | Ranked priorities per platform |
| 3:00 | Cross-platform dependencies and risks | Owners and dates |
| 3:30 | Decisions recap and open decision items | Decision items with needed-by dates |
| 3:50 | Retrospective on the review itself | One improvement |

## Attendees

Sponsor (chair), portfolio controls, flow lead, platform leads, lead architect, business owners, delivery leads as needed, contract oversight as an observer.

## Rules

- Decisions, not status. Status is in the pre-read.
- Every decision is recorded as a decision item with an owner.
- Finish on time. Anything unresolved becomes a decision item with a needed-by date.


---