Siemens Health Services
Moved from time-boxed Scrum with story points to the Kanban Method with WIP limits, flow metrics and Monte Carlo release forecasts.
- Throughput up 33%
- First release on schedule and 10% under budget
- About 70% less time on tool administration
- Found no useful correlation between story points and cycle time
Why it matters: Large, regulated, multi-team and release-driven: close to the conditions of most large enterprise delivery.
Source: Agile Alliance experience reportStrong