The off-boarding playbook

Five phases, four gates and a checklist for each. Built so that nobody changes how they work until the evidence says it's time.

Five phases with a gate between each: Align, Design and build, Prove, Cut over, Stabilize and evolve Direction endorsedDesign approvedGo or no-go90-day review1Align4 to 8 weeks2Design and buildAbout one quarter3ProveAbout one quarter4Cut overOne quarter5Stabilize and evolveOngoing

Choosing the cutover point

Cut over at an increment boundary

Let the current increment finish. Replace the next PI Planning event with the first quarterly business review.

Never during a major launch

If a big launch, migration, peak season or audit is in flight, protect it. Run the pilot, then cut over the quarter after it settles.

Change tools once

If you are moving to a new work tracker or hosting model, build the new model there so people learn the new tool and the new way once.

Bring governance with you

If a policy, contract or audit requirement names a framework, agree the documented approach before cutover and report both sets of measures for one quarter.

Have a fallback

Write down what happens if the go or no-go gate says no: keep the current cadence for one more quarter and try again.

Download as a workbook

Phase 1: Align

4 to 8 weeks

Agree the direction, name an owner, start measuring today, and find the constraints you must respect.

Where AI helps in this phase

  • Estimate planning hours from calendar exports and invite lists
  • Pull a flow baseline from tracker history
  • Scan policies and contracts for clauses that name a framework

Prompts for each step

Gate: Direction endorsed

The sponsor endorses the direction and the cutover target; the working group is chartered; baseline measures are collecting.

Phase 2: Design and build

About one quarter

Design cadences, lanes, roles, decision rights and the work-item model. Build it in your tools. Bring governance in early.

Where AI helps in this phase

  • Draft role guides and decision rights from the templates
  • Sort the existing backlog into the four lanes for review
  • Turn current increment objectives into a draft milestone register

Prompts for each step

Gate: Design approved

Operating model v1, work-item model and dashboards approved; governance has reviewed the approach; training plan ready.

Phase 3: Prove

About one quarter

Pilot flow with a few teams while everyone else keeps the current cadence. Shorten the existing planning event. Rehearse the first quarterly review.

Where AI helps in this phase

  • Publish the weekly flow digest for the pilot teams
  • Draft the first quarterly business review pre-read
  • Compare forecasts with actuals and explain the gaps

Prompts for each step

Gate: Cutover go or no-go

At least two months of pilot data; tools ready; most staff trained; no major launch or migration in progress. If not, move cutover one quarter.

Phase 4: Cut over

One quarter

The first quarterly business review replaces PI Planning. All teams move to flow. New measures go into status reports.

Where AI helps in this phase

  • Generate the new status report sections from tracker data
  • Answer staff questions from the role guides and FAQ
  • Summarize the six-week staff pulse into themes

Prompts for each step

Gate: 90-day review

Planning hours, flow time, milestone health and staff pulse reviewed against the baseline; version 2 changes agreed.

Phase 5: Stabilize and evolve

Ongoing

Tune the model with data, tie next year's roadmap to the budget cycle, and wind down the enabling team.

Where AI helps in this phase

  • Draft the 90-day before-and-after summary
  • Spot ceremonies that no longer produce decisions
  • Suggest lane-split changes from a quarter of data

Prompts for each step

Common risks and how to handle them

RiskResponse
Policy, contract or audit language names the framework or its measuresAgree a documented delivery approach with governance; report old and new measures side by side for one quarter.
Staff read the change as role cutsSay plainly that roles are refocused, not cut. Publish role guides early. Hold sessions by role.
Architects and product leads don't adopt work itemsMake work items the only way to request a review or rank work. Show queue age at the monthly operating review.
Work tracker data is too poor for flow metricsStart the baseline early, simplify statuses, add only the required fields.
A major launch or migration slips into the cutover windowMove cutover one quarter. Keep the go or no-go gate honest.
Metrics get used to rate individualsTeam-level only, written into working agreements and the measurement policy.
Neighboring groups stay on the old framework and dependencies breakHold a short quarterly dependency session and invite their leads to the business review.
Leaders are too busy to decide in timeTrack decisions as work items with needed-by dates; escalate age at the operating review.
The new model grows its own ceremonyEvery event needs an owner, a decision and a time box. Review the list at 90 days and remove one.