Metrics
Measure flow, delivery and outcomes. Forecast from real throughput. Make leadership and architecture work measurable too.
What to measure
Fourteen measures in five groups. Start with a baseline quarter before setting targets. All of them come from data you already have: your work tracker's status history, release logs and incident records.
Outcomes
| Measure | Answers | Definition | Starting target | Reviewed |
|---|---|---|---|---|
| Milestone health | Will we hit the dates we promised? | Share of milestones on or ahead of baseline, plus forecast variance for each | Every milestone has a current forecast; reviewed monthly | Monthly |
| Forecast accuracy | Can people trust our forecasts? | Share of items finished by their 85% forecast date | 85% or better | Monthly |
Flow
| Measure | Answers | Definition | Starting target | Reviewed |
|---|---|---|---|---|
| Flow time | How long does work take once started? | Elapsed time from start to done, reported at the 85th percentile by item type | Falling trend; set a target after a baseline quarter | Weekly |
| Throughput | How much do we finish? | Items finished per week, by team or platform | Stable or rising | Weekly |
| Work in progress and age | Are we starting more than we finish? | Count of items in progress against limits; age of each in-progress item | No item older than twice the median without action | Daily |
Delivery
| Measure | Answers | Definition | Starting target | Reviewed |
|---|---|---|---|---|
| Deployment frequency | How often do we deliver to production? | Production deployments per week | Weekly or better, inside any release windows you must respect | Weekly |
| Lead time for changes | How quickly does a change reach users? | Time from merge or configuration approval to production | Under one week | Monthly |
| Change failure rate | How often do changes hurt? | Share of production changes that need remediation | 15% or lower | Monthly |
| Recovery time | How fast do we recover? | Time to restore service after a failed change | Under one day | Monthly |
Visible work
| Measure | Answers | Definition | Starting target | Reviewed |
|---|---|---|---|---|
| Architecture review age | Are architects a bottleneck? | Business days from review request to outcome | Within the service level, often 5 business days | Weekly |
| Decision lead time | Are leaders deciding in time? | Days from decision opened to decided, against the needed-by date | 90% decided by the needed-by date | Monthly |
| Ready backlog depth | Is there enough shaped work? | Weeks of delivery-ready work per platform | Two to six weeks | Monthly |
Cost of coordination
| Measure | Answers | Definition | Starting target | Reviewed |
|---|---|---|---|---|
| Planning hours | What does coordination cost us? | Hours spent in planning events and their preparation | A fraction of the hours spent before | Quarterly |
| Staff pulse | How are people experiencing the change? | A short quarterly survey on clarity, workload and confidence | Rising trend | Quarterly |
Monte Carlo forecaster
Paste your team's weekly throughput, the number of items finished each week, and ask either question. The simulation runs in your browser; nothing is sent anywhere.
The forecaster needs JavaScript. To do it by hand: randomly draw a past week's throughput, add it up week by week until the remaining items are done, repeat a few thousand times, and read the 85th percentile of the weeks taken.
What to retire
Velocity and story points
Easy to inflate, impossible to compare across teams, and weakly linked to elapsed time. Throughput and flow time answer the same questions with real data.
PI predictability (business value achieved)
Scores a plan against itself. A program can score near 100% while a real milestone slips. Report it alongside milestone health for one transition quarter, then drop it.
Business-value points on objectives
Subjective scores assigned in the planning room. Milestone health and business-owner acceptance replace them.
Individual productivity measures
Flow and delivery measures are for teams and systems. Using them to rate people distorts them quickly. Write this into your working agreements.
Ground rules
- Measures describe teams and systems, never individuals. Put that in writing.
- Report percentiles, not averages. The 85th percentile tells people what to plan around.
- Pair every speed measure with a quality measure: throughput with change failure rate, flow time with escaped defects.
- Show trends over at least a quarter before reacting. One bad week is noise.
- Report old and new measures side by side for one quarter so oversight can see the bridge.
- When AI speeds up building, watch item size. More, smaller items inflate throughput without delivering more; milestone health and flow time keep you honest.
- Add review load to the conversation: if AI produces changes faster than people can review them, flow time hides in the review column.